Booking Linen Production Capacity Before Chinese New Year 2027

Oct 19,2026

Production Planning Guide

Booking Linen Production Capacity Before Chinese New Year 2027

Execution guide for brand owners, sourcing managers and production teams · Linenwind, Dongguan

Chinese New Year 2027 falls on 6 February. For a linen apparel programme, the holiday itself is not the main risk. The risk is the eight-week window around it, when fabric mills, dyehouses, trim suppliers, sample rooms, sewing lines and freight forwarders all compress their work into a shorter calendar and then stop at different times. A factory that closes for two weeks can still add four to six weeks to your effective lead time if the fabric was not booked, the sample was not approved, or the line slot was never reserved.

This guide is an execution plan, not a general explanation of lead times. It sets out the 2027 cut-off timetable, the difference between booking capacity and placing an order, what can still be inserted after the cut-off, and how to protect a Q1 2027 launch that cannot slip. The numbers used here are the factory standards Linenwind works to: MOQ 60 pieces per style and colour, sampling in 7-12 days, bulk production in 25-35 days, and 35-60 days for a first order end to end.

If you already have a tech pack and a target delivery date, the practical answer is simple: decide the styles and colours by the end of October, book fabric and trims in November, and convert capacity to a firm purchase order in the first week of December. If you are still developing, the plan changes: you are no longer buying pre-holiday production, you are buying a priority slot after the restart. Both are workable, but they are different purchases. For the underlying mechanics of sampling, bulk and shipping, see our guide to linen clothing lead times.

[IMAGE_PLACEHOLDER alt="Wide shot of a linen garment factory planning board in early winter, with a Chinese New Year countdown calendar, colour-coded production tickets for cutting, sewing and finishing, fabric rolls stacked behind, and a merchandiser marking a cut-off date with a red pen"]
6 FebChinese New Year 2027
2-4 wksTypical factory closure
25-35Days bulk production
60Pieces MOQ per style / colour

Why Chinese New Year 2027 Is a Capacity Event, Not a Holiday

Three things make the 2027 holiday more demanding than a normal year-end. First, the date is early. Chinese New Year moves with the lunar calendar, and 6 February sits at the front of the usual range, which compresses January instead of giving factories a long post-Christmas run. Second, the labour market moves before the official holiday. Many migrant workers in Guangdong leave one to two weeks before the factory closes and return gradually after the Lantern Festival, which falls on 20 February 2027. The official holiday is a date range; the effective labour availability is a longer curve.

Third, the upstream chain closes on a different schedule from the garment factory. Fabric mills and dyehouses often stop earlier because they need time to finish large dye lots and cool down equipment. Trim suppliers, embroidery units, print shops and packaging printers frequently run with smaller teams in the last ten days. A sewing line that is technically open in the first week of February may be waiting for buttons, labels or a late dye lot. That is why a buyer who plans only around the sewing factory's closure date usually loses another two weeks somewhere else in the chain.

The commercial consequence is that capacity in November and December is not unlimited, and it is not allocated on a first-come, first-served basis in the simple sense. Factories allocate lines to customers who have firm fabric, approved samples and a deposit. A purchase order without fabric allocation is a place in a queue, not a production slot. The earlier you convert intent into a named slot, the less you pay in expediting, air freight and margin erosion later.

There is also a retail calendar collision. European and North American spring floorsets usually land between late January and mid-March. If your linen programme is part of that set, the goods need to leave China in December or early January, not after the holiday. A March delivery sounds comfortable until you subtract 30-35 days of ocean transit, port dwell and inland delivery. Working backwards is the only reliable method.

The 2027 Cut-Off Timetable

The table below is the working calendar we recommend for programmes that must ship before the holiday. It is built around a 15 January ex-factory target, which leaves room for ocean transit and a buffer before a March floorset. Dates are planning cut-offs, not a substitute for the written schedule your factory issues in November. Confirm every date in writing, because individual mills, dyehouses and forwarders set their own last-accepted dates.

WindowWhat happensBuyer actionOutput required
Now to 31 October 2026Development, fabric selection and sample approval for pre-holiday productionLock the style, colour and fabric shortlist; request swatches and lab dips; confirm MOQ and target FOBApproved or near-approved sample; fabric quality chosen
1-13 November 2026Fabric and trim booking; dye-lot reservation; packaging specificationPlace fabric and trim orders against the forecast; approve bulk fabric and trimsFabric allocation confirmed; trim PO issued
14-27 November 2026Pre-production samples, size sets and final commentsConsolidate fit comments into one round; approve PP sample; confirm labels and packingSigned PP sample; final colour and trim approval
28 November-11 December 2026Bulk purchase order, deposit and line-slot confirmationConvert the forecast into a firm PO; pay deposit; get the line slot and weekly output plan in writingFirm PO; deposit received; named production slot
12 December 2026-15 January 2027Cutting, sewing, finishing, inline and final inspectionApprove weekly WIP reports; book inspection; prepare shipping documentsGoods packed and inspected; ex-factory date met
16 January-4 February 2027Logistics peak; port cut-offs; pre-holiday cargo surgeBook ocean freight early; confirm container pick-up; avoid last-minute document changesContainer loaded; documents issued
5-21 February 2027Holiday closure and slow restart (dates vary by factory)Do not plan new development, approvals or inspections in this windowPost-holiday schedule confirmed
22 February-8 March 2027Labour ramp-up; backlog clearing; post-holiday productionConfirm restart date and first-week output; prioritise repeat stylesRevised delivery schedule for post-CNY orders

The 15 January ex-factory target is an example. If your retail date is later, move the whole chain, not only the shipping booking. For a broader view of how each production stage consumes calendar time, see the clothing production timeline.

What Actually Stops During the Holiday, and What Does Not

Buyers often assume that the only closed operation is the sewing floor. In practice, the supply chain stops in layers. Understanding those layers is what separates a realistic schedule from an optimistic one.

FunctionTypical status around the holidayPractical consequence for buyers
Sewing and finishing linesStop for the holiday period; output falls before the closure and ramps slowly afterBulk production must be completed before the stop or scheduled after the restart
Sample roomUsually stops earlier than bulk because pattern makers and technicians travel firstNew fits, revisions and PP samples are effectively frozen from mid-December
Fabric millsClose earlier than garment factories; reopen later because of maintenance and labour returnFabric booked in January arrives after the holiday, not during it
DyehousesLonger closure; dye-lot scheduling tightens in DecemberNew colours and late lab dips are the most common cause of missed ex-factory dates
Trims, labels and packagingSmaller teams, reduced dispatch, often closed for the full periodA missing care label can hold a finished order for two weeks
Printing and embroideryOften subcontracted, with independent closure datesDecorative processes need their own cut-off, earlier than sewing
QC and inspectionSkeleton staff; third-party inspection slots fill upBook final inspection before the production end date, not after
Ports and forwardersPorts operate, but bookings, trucking and documentation slow downPre-holiday cargo surge and blank sailings can roll a container into the next month

The lesson is to plan the whole chain, not the factory gate. A garment that is 95% complete when the sample room closes is not 95% delivered. It is a garment waiting for one operation that nobody can perform until the restart.

The effective lead time in December is not the standard 25-35 days of bulk production. It is the standard production time plus the queue in front of you, plus the closure, plus the restart curve. Capacity booking is how you remove the queue from that equation.

Build Your Timetable Backwards from the Retail Date

Start with the date the goods must be on the shelf, not the date you would like to order. Subtract inland delivery, port dwell, ocean transit, ex-factory to port, inspection and packing, bulk production, pre-production sampling and fabric booking. What remains is the latest date for a firm purchase order. The formula is simple, but the buffer is where most plans fail.

  1. Retail or warehouse receipt date.
  2. Minus inland delivery and distribution centre appointment, typically 3-10 days depending on the market.
  3. Minus port dwell and customs clearance, typically 5-10 days for ocean freight.
  4. Minus ocean transit, which varies by lane and should be taken from your forwarder's current schedule, not a generic table.
  5. Minus ex-factory to port and container loading, typically 2-5 days.
  6. Minus final inspection and packing, typically 2-4 days.
  7. Minus bulk production, 25-35 days for linen garments after fabric is available.
  8. Minus PP sample and approval, typically 7-14 days including shipping the sample.
  9. Minus fabric and trim booking, typically 10-20 days for stock qualities and longer for dyed-to-order.

A worked example makes the compression visible. Suppose a European retailer needs goods in its warehouse by 15 March 2027. Allow 7 days for inland delivery and DC booking, 7 days for port and clearance, 32 days of ocean transit, 3 days to port, 3 days for inspection and packing, 30 days of bulk production, 10 days for PP approval and 14 days for fabric booking. The latest firm PO date is around 15 December 2026, and the fabric decision has to be made in late November. If any one of those stages slips by a week, the retail date is at risk unless a faster shipping mode is used.

  • Add five working days of buffer before the ex-factory date for finishing and inspection, not after it.
  • Add one full week of buffer before the retail date for port dwell and inland delivery.
  • Treat any custom colour, custom weave or new trim as a separate lead time, not as part of the garment lead time.
  • Confirm every date with the party that controls it: the mill controls the fabric lot, the dyehouse controls the colour, the factory controls the line, and the forwarder controls the sailing.
Shipping approachPlanning transitBest useTrade-off
Ocean FCLTypically 4-6 weeks door to door depending on laneFull programmes, repeat orders, cost-sensitive volumeLongest planning horizon; needs an early PO and early booking
Ocean LCLTypically 5-7 weeks door to doorSmaller capsules and mixed SKU ordersConsolidation adds dwell time and handling risk
Air freightTypically 5-10 days door to doorTop-up quantities, launch samples, a shortfall on a hero styleUsually several times the cost per kilogram of ocean freight
Rail or sea-airTypically 3-5 weeks depending on routingInland European destinations where the lane fitsLimited capacity and less predictable than direct ocean

Transit ranges are planning figures, not quotations. Lane, season, carrier and port congestion change the real number. Ask your forwarder for a dated schedule before you fix the retail date.

Fabric Is the Real Bottleneck

Linenwind keeps more than 50 fabric qualities in stock across the 100-260 gsm band, which removes the weave minimum for many programmes. Stock availability is not the same as unlimited availability. A stock quality in a natural or piece-dyed colour can be cut quickly; a custom colour, a special width, a yarn-dyed stripe or a new finish needs a dye lot and a production slot. In December, the difference between those two routes is often two to four weeks.

The fabric decision has three layers. The quality is the weave, weight and composition. The colour is the dye route and the lab dip. The lot is the actual batch of fabric reserved for your order. Buyers routinely approve the first two and leave the third until production starts, which is how two styles in the same colour end up with a visible shade difference. If the styles will be merchandised together, reserve the same dye lot for both, even if it means producing them in one block.

Shrinkage belongs in the same conversation. Untreated linen typically moves 3-7% on the first wash. A garment-washed or pre-shrunk finish can reduce that, but the finish itself consumes time and capacity. If your fit depends on a specific shrinkage result, test the actual bulk fabric, not a previous season's quality. Our explanation of linen fabric testing covers the tests to request before the fabric is cut.

Fabric routeMain lead-time driverRecommended booking pointRisk if left late
Stock quality, stock colourWarehouse picking and cutting approvalBy 13 November 2026Low, but the colour can sell out across multiple buyers
Stock quality, custom piece-dyeLab dip, dye-lot scheduling, finishingBy 6 November 2026Medium to high; December dyehouse queues are the bottleneck
Custom weave or yarn-dyed stripeWeaving slot, minimum run, samplingBy 31 October 2026High; a missed weave slot moves the order past the holiday
Special finish or washFinishing line capacity and testingBy 13 November 2026Medium; the finish may be available but the line slot is not
Repeat colour from a previous orderDye-lot continuity and fabric reservationBy 20 November 2026Low if the mill held the recipe; high if the lot was sold

A fabric order is not a reservation until a lot number and a delivery date are attached. Ask for both, and check that the lot is allocated to your order rather than to a general stock position.

Capacity Locks: How to Reserve a Line Without Overcommitting

Capacity is measured in sewing minutes, not in pieces. A factory can hold a line for a customer, but only if it knows the style, the operation count, the fabric arrival date and the ship window. That is why a vague forecast does not reserve anything. A capacity lock is a short agreement that converts a forecast into a named slot, with a deadline for turning it into a firm order.

The structure that works for both sides has five parts. First, a rolling forecast by style, colour and month, updated every two weeks. Second, a reservation deposit or option fee that is credited against the bulk order if the forecast converts. Third, a conversion deadline: the date by which the PO, deposit and approved PP sample must be in place, after which the slot is released. Fourth, a named line allocation and a weekly output plan, so the buyer can see what the factory has actually reserved. Fifth, a substitution rule for colour or style changes, so that a late change does not silently consume another customer's capacity.

For a small brand, the minimum commitment is usually expressed in pieces rather than line time. At 60 pieces per style and colour, a four-style capsule is 240 pieces before any size grading or repeat colour. That is a manageable lock if the styles share a fabric quality and a colour story, because the factory can cut them in one block. It becomes expensive if every style needs a different quality, a different trim and a different dye lot. Consolidation is the cheapest form of capacity planning.

Ask for the lock in writing, and make it specific. “We will try to fit you in” is not a reservation. “Line 3, week 49, 1,200 pieces of style A in natural and oatmeal, fabric lot allocated by 20 November, PO by 4 December” is a reservation. The second version can be managed; the first cannot.

A purchase order reserves money, not capacity. Capacity is reserved when a line, a week, a fabric lot and a conversion deadline are all named.

Insertion Orders: What Can Still Be Added After the Cut-Off

Not every buyer will be ready in November. Some will approve a sample in December, discover a bestseller that needs replenishment in January, or decide to add a colour after seeing the first production. The question is not whether late orders are possible, but what they cost and what has to be simplified.

Insertion optionWhat it requiresTypical timingTrade-off
Repeat style in a stock fabricExisting pattern, approved fit, fabric in stockCan be inserted until the line is fullLimited to colours already in the warehouse
Colour swap within an approved qualityLab dip or stock colour approval; same fabric lot if possibleEarly December at the latestShade continuity risk if the lot changes
Reduced trim or packaging specificationSimplified labels, buttons or polybagMid-December for pre-holiday finishingLower perceived value; not suitable for gifting
Split shipmentPartial quantity ready before the holiday, balance afterDecision by early JanuaryTwo sets of documents and two freight bookings
Air-freight top-upSmall quantity, light weight, priority finishingJanuary, while the line is still runningFreight cost can erase the margin on the top-up
Post-holiday priority slotCapacity reservation for the restartBook by mid-JanuaryDelivery moves to March or later

What cannot be inserted after mid-December is a new silhouette, a new fabric quality, a new print or a new packaging structure. Each of those needs a development cycle that the sample room cannot complete during the closure. If the design is not approved by the first week of December, the realistic plan is a post-holiday delivery, not a pre-holiday rush.

MOQ still applies to insertion orders. A late top-up of 60 pieces per style and colour is possible; a late top-up of 15 pieces in three colours is not, because the cutting and sewing set-up costs do not change. Our guide to linen clothing MOQ explains how the minimum is built and where it can be shared across styles.

Sampling and Approvals Before the Freeze

Sampling is the stage most often underestimated in a Chinese New Year plan, because it looks short on paper. A made-up sample takes 7-12 days, with a 7-14 day window depending on fabric availability. That is only the first sample. Fit approval, revisions, a second sample and PP approval can add another two to three weeks. If the first sample arrives in mid-December, the programme is already past the practical cut-off for pre-holiday bulk.

The approval sequence should be compressed deliberately, not accidentally. Consolidate fit comments into one round instead of sending three emails with overlapping changes. Approve the fabric and the trim at the same time as the fit, not after it. Ask for the PP sample before the bulk fabric is cut, and make sure the PP sample uses the actual production fabric and the actual trims. A PP sample made from a different dye lot is not a PP sample; it is a second fit sample.

Plan the calendar backwards from the sample room's last working day. If the factory stops sampling around 18 December, the last realistic date for a first sample request is the end of November. If the style is new and the fabric is not yet chosen, the end of October is the real deadline. The same logic applies to lab dips: a new colour requested in December will be processed after the restart, not before the holiday.

The sample room is the first part of the factory to feel the holiday and the last part to recover. Treat sampling as a November task, not a December one.

Shipping and Documents Before and After the Holiday

Ocean freight is a capacity market in the weeks before Chinese New Year. Space fills, rates firm, and blank sailings around the holiday reduce the number of departures. The mistake is to wait until the goods are ready before booking. By then, the earliest available sailing may be two or three weeks later, and the container may miss the retail window even though production finished on time.

Book the sailing when the production schedule is confirmed, not when the goods are packed. Confirm the container pick-up date with the factory, the cut-off at the port, and the documentation deadline. If the order is FOB, the forwarder is appointed by the buyer and the factory needs the booking number early enough to plan loading. If the order is EXW, the buyer owns the whole logistics chain and should be even more conservative with the dates.

Documents deserve the same attention. Commercial invoice, packing list, bill of lading, certificate of origin and any product test reports should be drafted before the holiday, not after. A missing certificate or a mismatch between the invoice and the packing list can hold a container at destination for longer than the production savings were worth. Our guide to importing linen clothing from China covers the document set and Incoterms in more detail.

For urgent top-ups, air freight is a legitimate tool, but it should be used for a defined shortfall, not as a rescue plan for a late start. The cost per kilogram is usually several times the ocean rate, and the chargeable weight of a linen garment order adds up quickly because linen is not a light fabric. Decide the air budget before the season, and reserve it for the styles where a stock-out would cost more than the freight. If short lead time is the core requirement rather than a one-off recovery, the production model behind fast production linen loungewear is a useful reference for how capacity, fabric and trims have to be pre-positioned.

Risk Register for a Pre-Holiday Linen Programme

The risks below are the ones that most often turn a workable plan into a missed date. Each has an early signal that can be seen weeks before the failure, which is what makes it manageable.

RiskEarly signalImpactMitigation
Fabric lot not allocatedSupplier gives a delivery week but no lot numberCutting cannot start; the whole schedule movesRequire a lot number and a written allocation date
Dye lot mismatch across stylesTwo styles approved from different lab dipsVisible shade difference at retailReserve one lot for the colour story; produce in one block
Sample rejection in DecemberFit comments arrive in more than one roundNo time for a second sample before the freezeConsolidate comments; approve fabric and trim with the fit
Trim or label shortageSupplier confirms a date after the sewing startFinished garments held for a low-cost componentOrder trims with the fabric; keep a small safety stock
Port rollover or blank sailingForwarder cannot confirm a vessel or cut-offTwo to three weeks of delay at the worst momentBook early; hold a backup sailing; consider sea-air
Factory closure extendsRestart date is described as “after the holiday”Post-holiday orders slip furtherGet a written restart date and a first-week output plan
Quality failure at final inspectionInline defect rate rises in the last weekRework or rejection with no time to replaceInline QC from the first output; AQL 2.5 checkpoints
Document errorInvoice and packing list differ on quantity or valueCustoms hold at destinationDraft and cross-check documents before the holiday

A Twelve-Week Action Plan

The plan below starts in the third week of October and runs to the middle of January. It assumes a pre-holiday ex-factory date and a first order rather than a repeat. Compress it only if the fabric is already in stock and the sample is already approved.

Week startingActionOwnerOutput
19 October 2026Confirm styles, colours and fabric shortlist; request swatches and lab dipsBrand and sourcingFabric decision shortlist
26 October 2026Approve first samples; confirm MOQ, FOB and packaging directionBrandApproved or revised sample comments
2 November 2026Place fabric and trim orders; confirm dye-lot availabilitySourcing and factoryFabric allocation and trim PO
9 November 2026Approve bulk fabric and trims; finalise size gradingBrand and technicalBulk fabric approval
16 November 2026PP sample review; consolidate fit and workmanship commentsBrandSingle comment round
23 November 2026Approve PP sample; confirm labels, hangtags and packingBrandSigned PP sample
30 November 2026Issue firm PO and deposit; confirm line slot and weekly outputBrand and factoryCapacity lock converted to order
7 December 2026Cutting starts; inline QC begins at first outputFactoryFirst cutting report
14 December 2026Book ocean freight and confirm port cut-offBuyer or forwarderBooking confirmation
21 December 2026Monitor WIP; resolve trim or quality issues immediatelyFactory and buyerWeekly WIP report
28 December 2026Pre-final inspection; correct any outstanding defectsFactory and QCInspection report
4 January 2027Final inspection and packing; prepare documentsQC and shippingPassed inspection; document set
11 January 2027Ex-factory and container loadingFactory and forwarderGoods departed

Two details make the plan work. First, the fabric order in week three of November is not a formality; it is the point at which the schedule becomes real. Second, the freight booking in mid-December is not early. It is the last comfortable window before the pre-holiday surge. If either slips, the ex-factory date is still possible, but the retail date is not.

The Cost of Waiting

Late decisions do not always appear as a higher FOB. They appear as air freight, expediting fees, split shipments, markdowns on a late launch, and management time spent chasing a schedule that has already been lost. The visible unit price can look identical while the landed cost rises.

Three costs are worth modelling before you decide to wait. The first is freight mode. If a two-week production delay forces a switch from ocean to air for even part of the order, the freight delta can be larger than the entire margin on those units. The second is retail timing. A spring linen programme that arrives after the floorset loses full-price selling weeks, and those weeks are usually the most profitable. The third is rework. A late order that is rushed through finishing and inspection has a higher chance of a quality failure, which creates its own replacement and freight cost.

There is also a hidden cost in the factory relationship. A customer who reserves capacity, confirms fabric and converts on time is easier to prioritise than a customer who holds an option and then changes the colour in December. That reliability has value in the next season, when capacity is tight again. Capacity planning is a repeated game, not a one-off negotiation, and the same discipline carries into scaling a linen brand from first order to repeat production.

The cheapest order is not the one with the lowest quoted FOB. It is the one that lands on the planned date, in the planned quantity, without a second freight booking.

[IMAGE_PLACEHOLDER alt="Factory loading bay in January with packed linen garment cartons on pallets, a container being loaded, a shipping document folder on a table, and a wall calendar showing the Chinese New Year date circled in red"]

Common Questions

When is Chinese New Year 2027, and how long do linen factories close?

Chinese New Year 2027 falls on 6 February. Factory closures typically run from two to four weeks, but the effective disruption is longer: workers leave before the official holiday and return gradually after the Lantern Festival on 20 February. Fabric mills and dyehouses often close earlier and reopen later than garment factories, so plan for a four-to-six-week productivity dip rather than a single holiday week.

What is the latest date to place a linen order for pre-holiday shipment?

For a programme that must leave the factory by mid-January, the firm purchase order should be in place by the first week of December, with fabric and trims booked in November and the PP sample approved before the PO. If the style is new or the fabric is custom, move those dates two to four weeks earlier. A late-December PO is usually a post-holiday delivery, even if the factory accepts it.

Does the whole supply chain stop during Chinese New Year?

Not at the same time, which is the problem. Sewing lines stop for the holiday, the sample room often stops earlier, fabric mills and dyehouses close on their own schedules, and trims, printing and packaging suppliers may run with reduced teams. Ports keep operating, but bookings and trucking slow down. A factory that is open can still be waiting for a button, a label or a dye lot.

Can I reserve capacity before the design is final?

Yes, but the reservation has to be specific enough to schedule. A useful capacity lock names the style family, the expected quantity, the fabric quality, the colour direction and the ship window, with a conversion deadline and a deposit or option fee. A vague forecast does not hold a line. The reservation becomes a firm order when the PO, deposit and approved PP sample are in place.

What happens if my sample is rejected in December?

There is usually no time for a second sample before the sample room closes. The practical options are to approve with a minor correction that can be handled in production, to simplify the style so it can be cut from an existing pattern, or to move the delivery to after the holiday. A new silhouette or a new fabric quality rejected in December cannot be rescued by pressure on the factory.

Is air freight worth it for a small linen order?

It can be, for a defined shortfall on a hero style where a stock-out would cost more than the freight. It is rarely sensible for a full programme, because linen is relatively heavy and the chargeable weight adds up. Decide the air budget before the season and reserve it for the few styles where speed protects revenue.

How much extra does a post-holiday delivery cost?

The FOB may not change, but the landed cost can. A later delivery may miss the first floorset, reduce full-price selling weeks, or force a split shipment and a second freight booking. The exact delta depends on the retail calendar and the freight market, so model it per order rather than applying a fixed percentage.

What should I confirm in writing with my factory?

Confirm the fabric lot and allocation date, the PP sample approval date, the line slot and weekly output, the ex-factory date, the factory closure and restart dates, the inspection date, and the document deadline. Ask for the name of the person responsible for each date. A schedule without owners is a wish list.

Next Step

If your Q1 2027 linen programme has a fixed retail date, the next decision is not the price. It is whether the fabric and the line slot are real. Send the style list, the target quantity and the delivery date, and we will map them against the pre-holiday calendar, confirm the fabric route and tell you which dates are still achievable. If the pre-holiday window has already closed, we will say so and propose a post-holiday slot rather than promise a date the supply chain cannot hold.

We reply to a complete brief within 48 hours and issue a formal quotation in 3-7 working days. Sampling runs 7-12 days, bulk production 25-35 days, and a first order typically takes 35-60 days end to end. Start with the contact form and put your target ex-factory date in the first message.